320 North 82nd Street Rehabilitation Project
320 N. 82nd Street Rehabilitation Progress

Project: Pump Station F-10 Rehabilitation
Construction Cost: $188,271.00
Anticipated Completion Date: Summer 2023
Contractor: Haier Plumbing & Heating
Major Rehabilitation Type: 4
- Wetwell
- Valve Vaults
- Pumps
- Control Panel
- Valves
- Electrical
- Force main
Rehab Type:
- Minor Rehab (guide rails, float switches, control panel repairs, etc)
- Partial Rehab (pump, control panel, guide rails, float switches, electrical, etc)
- Full Rehab (Pumps, control panel, valves, guide rails, float switches, electrical, etc)
- Major Rehab (wetwell, valve vault, pumps, control panel, valves, electrical, fencing, etc)
- Extensive Rehab (wetwells, valves vaults, pumps, control panels, valves, electrical, Force main, etc)
320 North 82nd Street Rehabilitation Progress
Excavating
0%
Wet Well Installation
0%
Valve Vault Installation
0%
Valve Installation
0%
Backfilling
0%
Inspection of Pump Station
0%
Pump Installation
0%
Control Panel Installation
0%
Electrical Control Panel Installation
0%
Testing
0%
Surface Restoration
0%
Cahokia Heights Funded Project Completion
320 North82nd Street Rehabilitation Project Completion
0%


The City of Cahokia Heights City Hall
103 Main St, Cahokia, IL 62206
Phone: (618) 332.4258
Hours:
Monday – Friday, 8:30 am – 4:30 pm
Email: Info@cahokiaheightsil.us
Recent Jobs
City Officials
The Start of Something New.
Copyright © 2024 - City of Cahokia Heights, IL | Mayor Curtis McCall Sr.